PROJECT PROGRESS

slide (7)

June 2020 - Site Progress

The Recovery Movement Control Order (RMCO) has been extended to 31st August, 2020 and construction works on site have resumed and progressing well with ample manpower

WhatsApp 2

May 2020 - Site Progress

The Conditional Movement Control Order (CMCO) has been extended to 9th June, 2020. The Government has made it mandatory for foreign workers to be tested for Covid19. The test was conducted on 17th May, 2020 and all foreign workers tested negative on 28th May, 2020. All consultants, subcontractors and suppliers must also submit proof of negative Covid19 tests before being allowed into the site.

WhatsApp Image 1

April 2020 - Site Progress

Even under MCO, the Main Contractor has been diligently checking on the health of workers at site daily. They have obtained approval to start work from MITI on 18th April, 2020 and the Group obtained its approval on 27th April, 2020.

photo 1

March 2020 - Site Progress

Progress of work as shown was taken before the Government announced the imposition of Movement Control Order on 18th March, 2020 to combat the Covid-19 pandemic, since then the construction works at site has stopped.

LG1 – in Zone 2 in progress & STP structure completed

February 2020 – Site Progress

LG2 slab completed and ramp for LG1 & LG2 in progress.

Apply_water_proofing_to_wall

January 2020 – Site Progress

Completion of work below ground level of the said Building (Stage 2a of the SPA).

2_Aerial_view_with_Jelutong_Villa,_Damansara_Villa_Peninsula_Hotel__10_Semantan_in_clockwise_order

December 2019 – Aerial View

Capturing the progress of site works from the air - presented by the main contractor.

WhatsApp_Image__(aerial_view_of_site_photo_2)

December 2019 – Site Progress

Works progressing well on the 2 level of carpark in LG1 and LG2.

16-11-19-zone-2-LG-3

November 2019 – Site Progress

Our first series of photos of site progress to keep your visually informed.