PROJECT PROGRESS

IMG 1

November 2020 - Site Progress

The CMCO has been further extended to 6th December, 2020 and the Government also announced the testing of all foreign workers beginning 1 Dec 2020. Structural works for Block A and Block B have reached Level 2 and Level 5 respectively.

IMG-10

October 2020 - Site Progress

The Government has imposed Conditional Movement Control Order (CMCO) for 2 weeks beginning October 13th and has extended it to November 9th. The Main Contractor continues to adhere to the strict SOP of the CMCO .Construction of structural works for Block A is progressing well at Ground level while Block B has reached Level 3.The Temporary Measures For Reducing The Impact of Coronavirus Disease 2019(COVID19) Act2020 was gazetted on 23 Oct 2020 to reduce the impacts of the pandemic on those affected.

IMG-10

October 2020 - Site Progress

The Government has imposed Conditional Movement Control Order (CMCO) for 2 weeks beginning October 13th and has extended it to November 9th. The Main Contractor continues to adhere to the strict SOP of the CMCO .Construction of structural works for Block A is progressing well at Ground level while Block B has reached Level 3.The Temporary Measures For Reducing The Impact of Coronavirus Disease 2019(COVID19) Act2020 was gazetted on 23 Oct 2020 to reduce the impacts of the pandemic on those affected.

WhatsApp 10

September 2020 - Site Progress

Superstructure works on site progress smoothly. The structural framework for the ground floor units are in the advanced stage of completion. The main contractor has been imposing strict SOP on their workers before allowing them on the site. 

WhatsApp 7

August 2020 - Site Progress

The RMCO has been extended to 31st December, 2020 and the Main Contractor is trying to catch up during this period as strict SOPs have to be adhered to

photo 1A

July 2020 - Site Progress

With RMCO still in force, workers are required to adhere to strict compliance of SOP at the project site. CIDB visited site on 14/7/2020 and issued compliance certificate

slide (7)

June 2020 - Site Progress

The Recovery Movement Control Order (RMCO) has been extended to 31st August, 2020 and construction works on site have resumed and progressing well with ample manpower

WhatsApp 2

May 2020 - Site Progress

The Conditional Movement Control Order (CMCO) has been extended to 9th June, 2020. The Government has made it mandatory for foreign workers to be tested for Covid19. The test was conducted on 17th May, 2020 and all foreign workers tested negative on 28th May, 2020. All consultants, subcontractors and suppliers must also submit proof of negative Covid19 tests before being allowed into the site.

WhatsApp Image 1

April 2020 - Site Progress

Even under MCO, the Main Contractor has been diligently checking on the health of workers at site daily. They have obtained approval to start work from MITI on 18th April, 2020 and the Group obtained its approval on 27th April, 2020.

photo 1

March 2020 - Site Progress

Progress of work as shown was taken before the Government announced the imposition of Movement Control Order on 18th March, 2020 to combat the Covid-19 pandemic, since then the construction works at site has stopped.

LG1 – in Zone 2 in progress & STP structure completed

February 2020 – Site Progress

LG2 slab completed and ramp for LG1 & LG2 in progress.

Apply_water_proofing_to_wall

January 2020 – Site Progress

Completion of work below ground level of the said Building (Stage 2a of the SPA).

2_Aerial_view_with_Jelutong_Villa,_Damansara_Villa_Peninsula_Hotel__10_Semantan_in_clockwise_order

December 2019 – Aerial View

Capturing the progress of site works from the air - presented by the main contractor.

WhatsApp_Image__(aerial_view_of_site_photo_2)

December 2019 – Site Progress

Works progressing well on the 2 level of carpark in LG1 and LG2.

16-11-19-zone-2-LG-3

November 2019 – Site Progress

Our first series of photos of site progress to keep your visually informed.