All states except Sarawak are now under Movement Control Order (MCO) until 4th February, 2021. Structural works on Block A has reached the roof level while that of Block B has reached Level 9. Brickworks and M& E installations have reached Level 5 for Block B. Structural works for designer courtyard is in progress. Lifts have arrived in Port Klang and most of them have been transported to site.