July 2022 – Site Progress

August 2022 – Site Progress
September 2, 2022
June 2022 – Site Progress
June 30, 2022

Block A lifts have been inspected and approved by the authority in July, 2022 while Block B’s lifts are pending authority's inspection. The roof structure for the main entrance and gym are in progress. TNB is expected to complete its works by end August 2022 while waterworks is awaiting authority's tapping approval. Main contractor is focussing in finishing the internal works.

SIGN UP NOW