December 2022 – Site Progress

January 2023 – Site Progress
February 3, 2023
November 2022 – Site Progress
November 30, 2022

Physical pipe works for incoming water supply from Jalan Duta completed. Contractor now working on fulfilling all prerequisites for permanent water meter by this month. This is affecting the CCC for the project as permanent water supply is required for testing and authorities' clearance letters. Electrical installations are undergoing testing and commissioning this month. Workers are now rectifying defects identified by site team and cleaning up and maintenance works are ongoing.