PROJECT PROGRESS

pic 4

August 2021 - Site Progress

Klang Valley is still under 1st phase of the National Recovery Plan.More economic sectors have been allowed to reopen since 16 August, 2021. The main contractor is awaiting official approval to reccommence works. Meanwhile the site workers continue to carry out housekeeping works such as debris disposal, general cleaning and mosquitoes fogging. About 72% of the main contractor’s work force is fully vaccinated and another 16% has been given the first dosage.

photo 3july

July 2021 - Site Progress

Kuala Lumpur and Selangor are currently under 1st phase of the National Recovery Plan. There was no physical works on site. The workers are restricted to carrying out housekeeping works like debris clearance, general cleaning and mosquitoes fogging. The main contractor has obtained vaccination appointments for 90% of their work force and awaiting vaccination.

Image5

June 2021 - Site Progress

The Government announced a Full Movement Control Order (FMCO) from 1 June to 28 June 2021 and thereafter the country is now on the 1st phase of the National Recovery Plan. Works virtually came to a standstill at the project site. During the month of June, the main contractor has arranged Covid19 swab tests on site for its workers and all were tested negative. It was only able to conduct housekeeping works such as debris clearing and cleaning, mosquitoes fogging and delivery of building materials only.

IMG 1

May 2021 - Site Progress

Full Lockdown MCO announced by Government from 1 to 14 June 2021.This will affect all sectors including our project site. External brickwork completed for Block B. The external wall plastering has commenced for Block B while internal wall plastering works for both blocks and the common areas are in progress. The floor screeding has started on the ground level of Block B.Installation of plastered ceiling frame works is underway too.

photo 1

April 2021 - Site Progress

The Conditional Movement Control Order (CMCO) has again been extended to 17th May, 2021. External brickworks completed for Block A and has reached Level 9 for Block B. Wall plastering works is ongoing for both blocks, common area including the car park floors. Doors and windows frames are in place for Level 1 of Block A and have reached Level 7 in Block B. The lift installation for Block A is in its final stages of completion while the installation of the lifts’ guide rail for Block B is currently underway. Works on the project’s fire protection system is in progress and the wet riser pump in Block B has been successfully installed.

photo 1

March 2021 - Site Progress

The Conditional Movement Control Order (CMCO) has been extended to 14th April, 2021. Brickworks and M & E works are progressing to Level 2 for Block A while in Block B, it has reached Level 8. Internal plastering / skim coatwork has commenced in both blocks including the common areas. Setting up for lifts installation is currently underway. The fire protection system and cabling works in TNB substation are completed awaiting inspection from the authority.

IMG 1

February 2021 - Site Progress

The Conditional Movement Control Order (CMCO) has been extended to 4th March, 2021. The structural works for Block A has reached the roof level while for Block B, it has reached Level 10. Brickworks and M & E installations are well in progress. Request was made to TNB to brighten up Jalan Bukit Ledang from Jalan Duta to the site and TNB responded by cutting overhang branches immediately.

IMG-1

January 2021 - Site Progress

All states except Sarawak are now under Movement Control Order (MCO) until 4th February, 2021. Structural works on Block A has reached the roof level while that of Block B has reached Level 9. Brickworks and M& E installations have reached Level 5 for Block B. Structural works for designer courtyard is in progress. Lifts have arrived in Port Klang and most of them have been transported to site.

December 2020 - Site Progress

The CMCO has been further extended to 14 January 2021 for Wilayah Persekutuan. Site construction works have reached Level 3 for Block A and Level 8 for Block B respectively. Brickworks and plastering have commenced and the imported lifts have arrived in Port Klang.

IMG 1

November 2020 - Site Progress

The CMCO has been further extended to 6th December, 2020 and the Government also announced the testing of all foreign workers beginning 1 Dec 2020. Structural works for Block A and Block B have reached Level 2 and Level 5 respectively.

IMG-10

October 2020 - Site Progress

The Government has imposed Conditional Movement Control Order (CMCO) for 2 weeks beginning October 13th and has extended it to November 9th. The Main Contractor continues to adhere to the strict SOP of the CMCO .Construction of structural works for Block A is progressing well at Ground level while Block B has reached Level 3.The Temporary Measures For Reducing The Impact of Coronavirus Disease 2019(COVID19) Act2020 was gazetted on 23 Oct 2020 to reduce the impacts of the pandemic on those affected.

WhatsApp 10

September 2020 - Site Progress

Superstructure works on site progress smoothly. The structural framework for the ground floor units are in the advanced stage of completion. The main contractor has been imposing strict SOP on their workers before allowing them on the site. 

WhatsApp 7

August 2020 - Site Progress

The RMCO has been extended to 31st December, 2020 and the Main Contractor is trying to catch up during this period as strict SOPs have to be adhered to

photo 1A

July 2020 - Site Progress

With RMCO still in force, workers are required to adhere to strict compliance of SOP at the project site. CIDB visited site on 14/7/2020 and issued compliance certificate

slide (7)

June 2020 - Site Progress

The Recovery Movement Control Order (RMCO) has been extended to 31st August, 2020 and construction works on site have resumed and progressing well with ample manpower

WhatsApp 2

May 2020 - Site Progress

The Conditional Movement Control Order (CMCO) has been extended to 9th June, 2020. The Government has made it mandatory for foreign workers to be tested for Covid19. The test was conducted on 17th May, 2020 and all foreign workers tested negative on 28th May, 2020. All consultants, subcontractors and suppliers must also submit proof of negative Covid19 tests before being allowed into the site.

WhatsApp Image 1

April 2020 - Site Progress

Even under MCO, the Main Contractor has been diligently checking on the health of workers at site daily. They have obtained approval to start work from MITI on 18th April, 2020 and the Group obtained its approval on 27th April, 2020.

photo 1

March 2020 - Site Progress

Progress of work as shown was taken before the Government announced the imposition of Movement Control Order on 18th March, 2020 to combat the Covid-19 pandemic, since then the construction works at site has stopped.

LG1 – in Zone 2 in progress & STP structure completed

February 2020 – Site Progress

LG2 slab completed and ramp for LG1 & LG2 in progress.

Apply_water_proofing_to_wall

January 2020 – Site Progress

Completion of work below ground level of the said Building (Stage 2a of the SPA).

2_Aerial_view_with_Jelutong_Villa,_Damansara_Villa_Peninsula_Hotel__10_Semantan_in_clockwise_order

December 2019 – Aerial View

Capturing the progress of site works from the air - presented by the main contractor.

WhatsApp_Image__(aerial_view_of_site_photo_2)

December 2019 – Site Progress

Works progressing well on the 2 level of carpark in LG1 and LG2.

16-11-19-zone-2-LG-3

November 2019 – Site Progress

Our first series of photos of site progress to keep your visually informed.