August 2022 – Site Progress

September 2022 – Site Progress
September 30, 2022
July 2022 – Site Progress
August 1, 2022

TNB's works for the substation completed while water connection approval is in progress. Strata titles have been issued. Perimeter fencing is ongoing and physical works are expected to complete by end Sep 2022.