The shorter February month with CNY and FT Day holidays reduced the number of working days this month. Block B's external plastering is in the advance stage while the internal plastering and tiling works are on-going. The ID works to the Show Unit on the Ground Floor of Block B will be completed for viewing in March, 2022. The designer courtyard is progressively taking shape with the planting of trees.