June 2021 – Site Progress

July 2021 – Site Progress
July 29, 2021
May 2021 – Site Progress
May 31, 2021

The Government announced a Full Movement Control Order (FMCO) from 1 June to 28 June 2021 and thereafter the country is now on the 1st phase of the National Recovery Plan. Works virtually came to a standstill at the project site. During the month of June, the main contractor has arranged Covid19 swab tests on site for its workers and all were tested negative. It was only able to conduct housekeeping works such as debris clearing and cleaning, mosquitoes fogging and delivery of building materials only.