Painting works on the external walls of Block A is ongoing. The gym & sauna block is currently underway with the brick works in progress too. Water proofing works for the courtyard, the planter boxes and half Olympic size pool are progressing well. Landscaping works is targetted to commence in December 2021. Getting additional workers remains the main obstacle of the main contractor and its subcontractors with nationwide shortage.