November 2022 – Site Progress

December 2022 – Site Progress
January 3, 2023
October 2022 – Site Progress
October 31, 2022

Approval procurement to commence incoming main water supply works delayed due to GE15. Works is now expected to start only in 1st half December 2022. Final testing of M&E equipment such as air conditioning system, fire protection system, lift system, card access and others are being carried out. Contractor is also rectifying defects identified by the Developer and cleaning up all units. Wardrobe installation and completion delayed by manpower issues.