Klang Valley have moved to Phase 4 of the National Recovery Plan on 18th October 2021. The roof water proofing and water tightness test for Block A is currently underway. The internal and external wall plastering works of both the Blocks are in progress. Lift cars and lift motor installation for Block A in progress while in Block B, setting out works for installation is ongoing. Tiles and timber flooring works for the units have commenced.