October 2022 – Site Progress

November 2022 – Site Progress
November 30, 2022
September 2022 – Site Progress
September 30, 2022

TNB substation finally energised end October 2022 while individual meters will be installed in November 2022. Contractor awaiting go ahead to install incoming water supply from authorities. Completed units are being cleaned and touched up for CCC soon. Upgrading of lifts' lobbies at developer's costs ongoing to further improve the development.