April 2021 – Site Progress

May 2021 – Site Progress
May 31, 2021
March 2021 – Site Progress
April 1, 2021

The Conditional Movement Control Order (CMCO) has again been extended to 17th May, 2021. External brickworks completed for Block A and has reached Level 9 for Block B. Wall plastering works is ongoing for both blocks, common area including the car park floors. Doors and windows frames are in place for Level 1 of Block A and have reached Level 7 in Block B. The lift installation for Block A is in its final stages of completion while the installation of the lifts’ guide rail for Block B is currently underway. Works on the project’s fire protection system is in progress and the wet riser pump in Block B has been successfully installed.