March 2021 – Site Progress

April 2021 – Site Progress
May 3, 2021
February 2021 – Site Progress
February 26, 2021

The Conditional Movement Control Order (CMCO) has been extended to 14th April, 2021. Brickworks and M & E works are progressing to Level 2 for Block A while in Block B, it has reached Level 8. Internal plastering / skim coatwork has commenced in both blocks including the common areas. Setting up for lifts installation is currently underway. The fire protection system and cabling works in TNB substation are completed awaiting inspection from the authority.