The Conditional Movement Control Order (CMCO) has been extended to 4th March, 2021. The structural works for Block A has reached the roof level while for Block B, it has reached Level 10. Brickworks and M & E installations are well in progress. Request was made to TNB to brighten up Jalan Bukit Ledang from Jalan Duta to the site and TNB responded by cutting overhang branches immediately.